Brown County 2012 construction outlook
Main Avenue (County G) Interchange
March through November 2012
- Reconstruction of Main Avenue interchange; expand and improve park and ride lot
- Construction at the Main Avenue interchange is scheduled to begin March 5th (ramp will not close earlier than March 12).
- Main Avenue under US 41 will remain open with one lane of traffic in each direction
- The entire interchange and Main Avenue, including access across (under) US 41, will be CLOSED to traffic with no access to or from US 41 for 60 days between August and November
- The Lawrence Drive park and ride lot may be CLOSED from March to October–exact closure dates to be determined (see www.dot.wisconsin.gov/travel/parkride/brown.htm for alternate lots)
- Detour: access to and from US 41 available at Scheuring Road (County F) and Oneida Street (County AAA) with Glory Road and Grant Street providing access across US 41
US 41 Mainline
(Orange Lane to Glory Road – March 2012 through June 2013) (9th Street to Larsen Road – September 2011 through October 2012) (Larsen Road to Memorial Drive – August 2012 through August 2014)
- Reconstruction of the US 41 mainline, including construction to replace box culverts along the mainline and the 9th Street bridge
- The US 41 mainline will have two lanes of traffic in each direction with possible nighttime lane closures
Lakeview Drive Bridge Construction
August through December 2012
- Reconstruction of Lakeview Drive overpass
- Lakeview Drive at US 41 will be CLOSED while a new bridge is reconstructed over US 41
- Alternate routes across US 41 include Velp Avenue and Lineville Road
County RK and County J
June 2011 through May 2012
- Completion of the County RK and County J construction near WIS 29
- In spring of 2012, County J will CLOSE for six weeks north of WIS 29. County RK will remain open to traffic with intermittent lane closures for paving operations
- Alternate routes include County FF and Packerland Drive (County EB)
WIS 29 Mainline (County J to Duck Creek)
March through November 2012
- Reconstruction of the WIS 29 mainline
- Two lanes of traffic will be maintained on WIS 29 in each direction with possible nighttime lane closures
- Access to and from Packerland Drive (County EB) will be maintained
New Shawano Avenue and Packerland Drive
March through November 2012
- Construction of new Shawano Avenue, located north of the existing WIS 29 facility, along with ramps connecting Packerland Drive (County EB) with WIS 29 to and from the west
Mason Street (WIS 54) Interchange
February through August 2012
- Reconstruction of Mason Street interchange
- The Mason Street interchange, bridge and Mason/Taylor Streets intersection will be CLOSED starting in February and will reopen in August 2012
- Access to and from US 41 available at WIS 29 (Shawano Avenue) and Lombardi Avenue, along with access across US 41 at Larsen Road and 9th Street; some inter-mittent closures at 9th Street will occur
- Through traffic on WIS 54: WIS 172 to I-43 to WIS 54
Lombardi Avenue (County VK) Interchange
March through September 2012
- Reconstruction of Lombardi Avenue interchange.
- Lombardi Avenue will have two lanes open in each direction throughout construction, with possible lane reductions at night
- The one exception is from August to September when there will be one lane open in each direction along a short segment of Lombardi Avenue near Shady Lane
- Access to and from US 41 will be maintained
Winnebago County 2012 construction outlook
US 41 Mainline Paving US 45 to Breezewood Lane
April 2011 through June 2013
Witzel Avenue to US 45
August 2011 through July 2013
- Reconstruction of northbound US 41 lanes
- The US 41 mainline will have two lanes of traffic in each direction
- Expect periodic nighttime lane closures from 7 p.m. to 5 a.m.
US 45 Interchange
August 2010 through August 2012
- Completion of the interchange to provide free-flow movements between US 41 and US 45
- The northbound entrance and exit ramps at US 41 and the northbound flyover ramp to US 45 will be CLOSED until July 2012
Lake Butte des Morts Causeway
September 2011 through September 2013
- Construction began in September of 2011 on three new bridge structures on the new southbound lanes west of the existing roadway
- Two lanes of traffic will remain open in both directions, but lanes and shoulders will be narrow; motorists may experience temporary nighttime closures as trucks and equipment move in and out of the work zone
WIS 21 Interchange
August 2011 through November 2012
- Reconstruction of the existing interchange and roundabouts on WIS 21 and ramp ends, including bicycle and pedestrian accommodations
- This interchange will CLOSE from March 2012 through November 2012
- Movements to North Washburn Street/Brooks Lane and Rath Lane will always be available via WIS 21 and/or local street connection
|